Kadina Solar Farm

What looked like the perfect job, turned out to be just that!

With day one site inductions and pre-start meetings complete, the DRASOL construction crew of nine got off to a flying start by laying out a large portion of the field and installing five of the single-axis trackers by days end.

Fast-forward nineteen days and after a hand shake with the client and a thank you speech to the crew, the job was done!

DRASOL successfully installed 198 trackers and 15,845 PV modules, which was a new construction record for the company, some 5.8Mw in under three weeks from start to finish.

Andrew and David Farrer congratulate all the construction crew members involved for their hard working efforts during the build.